Solar Panel Configuration
The solar panel pole is supported by two star pickets driven into the ground
with wire ties passed through holes in the pole to prevent twisting.
The solar panel maounting sits on the top of the pole along with the GPS antenna.
The cables are brought down the face of the pole, secured with tapes and
then protected with a third star picket secured with two hose clamps.
The connections are bound to prevent ingress of water. The solar panel should be
8 metres or more from the seismometer pit.
Back to index
Cable Trench
The power cable from the solar panel and GPS cable are brought down the
pole and then run in a shallow trench extending from the solar panel to the
instrument package and then on to the seismometer pit.
This trench is usually started with a pick but may need
to be dug deeper.
The trench may need to have the cables snaked back on each other (depending on
length). The sections of the cables nearest to the instrument package are protected
with plastic tubing. The seismometer cable is similarly protected to the lip of the
seismometer pit.
The trenches are back filled to ensure coverage and protection of the cables.
it is important to make sure that the power and GPS cables are well protected
as they enter the ground, either with extra dirt or with stones etc.
Slabs of flat stone, when available, provide a useful protection of the cables.
The power cable needs to be brought to the battery from whence power is delivered to
the recorder and seismometer.
Back to index
Seismometers
The Tasman Line experiment uses 4 types of seismometers whose response
is flat to ground velocity of a broad band in frequency:
Streckeisen STS2 :- triaxial seismometer, very sensitive to tilt
Guralp CMG-3ESP :- with corner at 0.03 Hz, ESP+ corner at 0.015 Hz
- tilting causes problems on horizontal components
Guralp CMG-40T :- less sensitive and smaller
Nanometrics Trillium :- triaxial design
STS-2
The emplacement of the seismometer is a critical part of the site development.
As far as possible the seismometer pit should not be close to trees, and best
results are achieved when the ground is not soft, even though this makes digging the
pit more difficult. The hole needs to be excavated to a depth about 20 cm greater than
the height of the seismometer to allow room for the base plate and plastic cover.
Quick setting cement normally provides a good and stable base. The material has to
be mixed on site and made as smooth and level as possible as possible so that
the levelling legs on the seismometer can accommodate any minor irregularities.
The seismometer needs to be aligned so that the horizontal components are oriented
NS and EW, the details vary with the instrument but a siting bar set up with compass
bearing usually enables a field precision of 2 degrees or better. The correction for
magnetic north is important and needs to be applied in the correct sense.
The cable configurations differ between the different models, but in each case care
need to be taken to have a clean entry to the seismometer so that the plastic
cover can be put on with good contact with the base plate. Centering of the
mass requires a seismometer specific approach.
Once the seismometer is in position and the channels have been tested through the
recorder (with gentle ground movement) the plastic cover is put over the top
to provide mechanical protection and thermal insulation. For the STS2 an extra wrap
of insulation goes over the seismometer before the cover is applied.
Backfilling of earth around the seismometer cover needs to be carried out gently
and the material should be built up above the original ground surface.
In some circumstances it may be necessary to have the seismometer cover protuding
above the ground surface (e.g. shallow hard rock). The mound should then
be carefully shaped to minimise wind interaction.
Back to index
Recorders
Earth Data
Nanometrics Orion
Back to index
Site Protection
Back to index